| STANDPIPES |
| 1 | Standpipe frame bolts | GRS Engineering | | | GRS supplying with the frame |
| 2 | HDPE isolation pads (SS pipework ↔ galvanised frame) | GRS Engineering | | | Galvanic isolation |
| 3 | Stainless U-bolts (pipework to frame) | GRS Engineering | | | |
| 4 | Layflat off-take (discharge off SS pipework) | TBC | | | RFQ sent — chase quote |
| 5 | Bolts — valves & flanged connections | Ordered | | | |
| 6 | Nylon top-hat isolators (HDPE flange ↔ SS standpipe) | Design | | | Stops SS / galvanised contact at the bolt hole |
| 7 | M20 chemi-anchors (frame tie-down) | Ordered | | | |
| FLOW METER / ACTUATED VALVES |
| 8 | 316 SS saddles | Polyfit / GRS | | | Quotes from both — compare & choose |
| 9 | Bolts (valve / meter connections) | Polyfit | | | Included in Polyfit supply |
| 10 | M20 chemi-anchors (saddles → concrete plinths) | Ordered | | | |
| GASKETS |
| 11 | Spare gaskets — rubber, Table D | Effseal | | | 20×DN100 · 20×DN160 · 20×DN355 · 5×DN560 |
| CONSUMABLES |
| 12 | Project consumables | DTL | | | PO issued (attached by Sean) |
| 13 | DN560 roller sling | DTL | | | |
| SEA CONTAINER |
| 14 | Racking | DTL | | | Installed |
| 15 | Flammable segregation box | DTL | | | Installed |
| 16 | Signage | DTL | | | |